This week has mainly consisted of continuing the o drive monthly backup and updating the center office computers.
Tasks for the Week
Completed Tasks
✓ Microsoft updates on all center office computers
✓ Projector Inventory
Incomplete Tasks
✗ Install/run McAfee Anti-virus software on all center office computers (Completed 4 of 7)
✗ Windows updates on all center office computers (Completed 2 of 7)
✗ o drive backup
Problems Encountered
This week, I have not encountered any major issues. Due to the amount of time allotted for the set tasks, I had decided to test the amount of time required to complete updates on one of the center computers. After doing so, I had come to the conclusion that scheduling necessary restarts would be best for the Windows updates as long as they do not interfere with the workflow of the office.